WORKDAY.INTL

Returns the date a given number of working days before or after a start date, with a weekend you choose and optional holidays.

Syntax

=WORKDAY.INTL(, , , )

Date and time

Excel 2010 and later.

Try it

Edit the formula in C2 or change the inputs. The sheet recalculates as you type.

C2
A
B
C
1
Start
Days
Finish
2
03-Mar-2025
10
14-Mar-2025
3

C2 =WORKDAY.INTL(A2,B2,11) returns 14-Mar-2025

How WORKDAY.INTL works

WORKDAY.INTL returns the date that is a set number of working days away from a start date, like WORKDAY, but you decide which days of the week are days off. =WORKDAY.INTL(A2,10,11) moves ten working days in a six-day week where only Sunday is closed. Use it for Middle Eastern weekends, shift patterns, retail and part-time rotas.

The weekend argument

The weekend can be set in two ways.

A code. 1 (the default) is Saturday and Sunday. 2 to 7 pick two consecutive days: 2 is Sunday and Monday, and 7 is Friday and Saturday. 11 to 17 pick a single day: 11 is Sunday only, 12 Monday only, and 17 Saturday only.

A seven-character string. One character per weekday, Monday first. 1 is a day off and 0 is a working day. "0000011" is Saturday and Sunday, "0000110" is Friday and Saturday, and "0101011" is a Monday, Wednesday, Friday schedule. Use the string for patterns that codes can't express, such as days off that aren't next to each other. The string must be exactly seven characters of 0 and 1.

Start date, days and holidays

As in WORKDAY, the start date is not counted. =WORKDAY.INTL(A2,1,7) is the next working day after A2 under a Friday and Saturday weekend. A negative days moves backwards: =WORKDAY.INTL(B2,-5,11) is five working days before B2 in a six-day week. The optional holidays range removes extra days. Use real dates, and lock the range with dollar signs when filling down.

Starting on a day off

If the start date is itself a day off, counting begins from the next working day. Starting from a Saturday under the default weekend, one working day later is Monday. This is the same as WORKDAY.

When to use it

  • Standard Saturday and Sunday weekend: WORKDAY is shorter and works in every version.
  • Any other weekend or schedule: WORKDAY.INTL.
  • Counting days between two dates instead: NETWORKDAYS.INTL. It takes the same weekend and holiday arguments.

A planning example

A delivery team works Sunday to Thursday. For a 5-working-day lead time from an order date in A2, with holidays in a named range: =WORKDAY.INTL(A2,5,"0000110",Holidays). Friday and Saturday are marked 1, so the schedule skips them. The result is a serial number, so apply a date format.

Time of day on the start date is ignored. WORKDAY.INTL uses only the whole-number part of the date.

Arguments

start_date
The date to count from. The start date itself is not counted as one of the days.
days
The number of working days to move. Positive goes forward, negative goes back, and a fraction is cut off.
weekendoptional
Which days are days off. A number from the preset list, or a seven-character string. 1 or omitted: Saturday and Sunday. 7: Friday and Saturday. 11: Sunday only. 17: Saturday only. A string starts on Monday, with 1 for a day off and 0 for a working day: "0000011" is Saturday and Sunday.
holidaysoptional
A range of dates to treat as extra days off, such as F2:F10. Use real dates. A holiday on a weekend day changes nothing.

Examples

Each example is a live sheet. Change the inputs or the formula and watch the result.

Example 1

Six-day week: ten working days on

C2 =WORKDAY.INTL(A2,B2,11)

Result: 14-Mar-2025

Only Sunday is a day off, so Saturdays count. Ten working days after Monday 3 March is Friday 14 March 2025.

C2
A
B
C
1
Start
Days
Finish
2
03-Mar-2025
10
14-Mar-2025
3

C2 =WORKDAY.INTL(A2,B2,11) returns 14-Mar-2025

Example 2

Friday and Saturday weekend

C2 =WORKDAY.INTL(A2,B2,7)

Result: 10-Mar-2025

Sunday counts as a working day here. Starting on Monday 3 March, the five working days are 4, 5, 6 and 9 March and then 10 March, so the answer is 10-Mar-2025.

C2
A
B
C
1
Start
Days
Finish
2
03-Mar-2025
5
10-Mar-2025
3

C2 =WORKDAY.INTL(A2,B2,7) returns 10-Mar-2025

Example 3

A pattern string with a holiday

C2 =WORKDAY.INTL(A2,B2,"0000011",E2)

Result: 11-Mar-2025

The string "0000011" is the standard Saturday and Sunday weekend. Without the holiday the fifth working day is 10 March. With Monday 10 March off, it moves to Tuesday 11 March.

C2
A
B
C
D
E
1
Start
Days
Finish
Holiday
2
03-Mar-2025
5
11-Mar-2025
10-Mar-2025
3

C2 =WORKDAY.INTL(A2,B2,"0000011",E2) returns 11-Mar-2025

Example 4

Count backwards in a six-day week

C2 =WORKDAY.INTL(A2,-B2,11)

Result: 08-Mar-2025

Going back from Friday 14 March, the five working days before it are 13, 12, 11, 10 and Saturday 8 March. Sunday 9 March is skipped, so the answer is 8-Mar-2025.

C2
A
B
C
1
Deadline
Days needed
Start by
2
14-Mar-2025
5
08-Mar-2025
3

C2 =WORKDAY.INTL(A2,-B2,11) returns 08-Mar-2025

Your turn.

Solve it in the sheet. Every answer is checked, with hints if you need them.

Task 1 of 2

In C2, return the finish date for a six-day week (only Sunday off). Fill it down to C4.

Answer in C2, then it fills down to C4.

C2
A
B
C
D
E
1
Order date
Lead time (working days)
Six-day week
Fri-Sat weekend
2
03-Mar-2025
5
3
10-Mar-2025
8
4
24-Mar-2025
12
5

Common mistakes

  • The start date isn't counted. WORKDAY.INTL(A2,1,7) is the next working day after A2, not A2 itself.
  • The weekend string runs Monday to Sunday. "0000011" is Saturday and Sunday. Starting the string on Sunday gives the wrong days off.
  • A weekend string must be exactly seven characters of 0 and 1, otherwise the result is #VALUE!. Codes outside 1 to 7 and 11 to 17 return #NUM!.
  • If the weekend pattern comes from a cell, the cell must hold text. A typed number like 0000011 loses its leading zeros. Format the cell as Text first.
  • The result is a serial number. If a cell shows 45730, apply a date format.

Questions people ask

How do I add working days with a Friday and Saturday weekend?

Use `=WORKDAY.INTL(A2,10,7)`. Weekend code 7 sets Friday and Saturday as days off. The string `"0000110"` does the same.

How do I include Saturday as a working day?

Use weekend code 11 so that only Sunday is a day off: `=WORKDAY.INTL(A2,10,11)`.

What is the difference between WORKDAY and WORKDAY.INTL?

WORKDAY always skips Saturday and Sunday. WORKDAY.INTL has a weekend argument, so you can pick other days, or a pattern such as Monday, Wednesday, Friday.

Can WORKDAY.INTL count backwards?

Yes. Use a negative number of days. `=WORKDAY.INTL(A2,-5,11)` is five working days before A2 in a six-day week.