Example 1
Six-day week: ten working days on
C2 =WORKDAY.INTL(A2,B2,11)
Result: 14-Mar-2025
Only Sunday is a day off, so Saturdays count. Ten working days after Monday 3 March is Friday 14 March 2025.
C2 =WORKDAY.INTL(A2,B2,11) returns 14-Mar-2025
Returns the date a given number of working days before or after a start date, with a weekend you choose and optional holidays.
Syntax
=WORKDAY.INTL(, , , )
Excel 2010 and later.
Try it
Edit the formula in C2 or change the inputs. The sheet recalculates as you type.
C2 =WORKDAY.INTL(A2,B2,11) returns 14-Mar-2025
WORKDAY.INTL returns the date that is a set number of working days away from a start date, like WORKDAY, but you decide which days of the week are days off. =WORKDAY.INTL(A2,10,11) moves ten working days in a six-day week where only Sunday is closed. Use it for Middle Eastern weekends, shift patterns, retail and part-time rotas.
The weekend can be set in two ways.
A code. 1 (the default) is Saturday and Sunday. 2 to 7 pick two consecutive days: 2 is Sunday and Monday, and 7 is Friday and Saturday. 11 to 17 pick a single day: 11 is Sunday only, 12 Monday only, and 17 Saturday only.
A seven-character string. One character per weekday, Monday first. 1 is a day off and 0 is a working day. "0000011" is Saturday and Sunday, "0000110" is Friday and Saturday, and "0101011" is a Monday, Wednesday, Friday schedule. Use the string for patterns that codes can't express, such as days off that aren't next to each other. The string must be exactly seven characters of 0 and 1.
As in WORKDAY, the start date is not counted. =WORKDAY.INTL(A2,1,7) is the next working day after A2 under a Friday and Saturday weekend. A negative days moves backwards: =WORKDAY.INTL(B2,-5,11) is five working days before B2 in a six-day week. The optional holidays range removes extra days. Use real dates, and lock the range with dollar signs when filling down.
If the start date is itself a day off, counting begins from the next working day. Starting from a Saturday under the default weekend, one working day later is Monday. This is the same as WORKDAY.
A delivery team works Sunday to Thursday. For a 5-working-day lead time from an order date in A2, with holidays in a named range: =WORKDAY.INTL(A2,5,"0000110",Holidays). Friday and Saturday are marked 1, so the schedule skips them. The result is a serial number, so apply a date format.
Time of day on the start date is ignored. WORKDAY.INTL uses only the whole-number part of the date.
1 or omitted: Saturday and Sunday. 7: Friday and Saturday. 11: Sunday only. 17: Saturday only. A string starts on Monday, with 1 for a day off and 0 for a working day: "0000011" is Saturday and Sunday.F2:F10. Use real dates. A holiday on a weekend day changes nothing.Each example is a live sheet. Change the inputs or the formula and watch the result.
Example 1
C2 =WORKDAY.INTL(A2,B2,11)
Result: 14-Mar-2025
Only Sunday is a day off, so Saturdays count. Ten working days after Monday 3 March is Friday 14 March 2025.
C2 =WORKDAY.INTL(A2,B2,11) returns 14-Mar-2025
Example 2
C2 =WORKDAY.INTL(A2,B2,7)
Result: 10-Mar-2025
Sunday counts as a working day here. Starting on Monday 3 March, the five working days are 4, 5, 6 and 9 March and then 10 March, so the answer is 10-Mar-2025.
C2 =WORKDAY.INTL(A2,B2,7) returns 10-Mar-2025
Example 3
C2 =WORKDAY.INTL(A2,B2,"0000011",E2)
Result: 11-Mar-2025
The string "0000011" is the standard Saturday and Sunday weekend. Without the holiday the fifth working day is 10 March. With Monday 10 March off, it moves to Tuesday 11 March.
C2 =WORKDAY.INTL(A2,B2,"0000011",E2) returns 11-Mar-2025
Example 4
C2 =WORKDAY.INTL(A2,-B2,11)
Result: 08-Mar-2025
Going back from Friday 14 March, the five working days before it are 13, 12, 11, 10 and Saturday 8 March. Sunday 9 March is skipped, so the answer is 8-Mar-2025.
C2 =WORKDAY.INTL(A2,-B2,11) returns 08-Mar-2025
Solve it in the sheet. Every answer is checked, with hints if you need them.
Task 1 of 2
In C2, return the finish date for a six-day week (only Sunday off). Fill it down to C4.
Answer in C2, then it fills down to C4.
WORKDAY.INTL(A2,1,7) is the next working day after A2, not A2 itself."0000011" is Saturday and Sunday. Starting the string on Sunday gives the wrong days off.#VALUE!. Codes outside 1 to 7 and 11 to 17 return #NUM!.45730, apply a date format.Use `=WORKDAY.INTL(A2,10,7)`. Weekend code 7 sets Friday and Saturday as days off. The string `"0000110"` does the same.
Use weekend code 11 so that only Sunday is a day off: `=WORKDAY.INTL(A2,10,11)`.
WORKDAY always skips Saturday and Sunday. WORKDAY.INTL has a weekend argument, so you can pick other days, or a pattern such as Monday, Wednesday, Friday.
Yes. Use a negative number of days. `=WORKDAY.INTL(A2,-5,11)` is five working days before A2 in a six-day week.