WORKDAY

Returns the date a given number of working days before or after a start date, skipping weekends and any holidays you list.

Syntax

=WORKDAY(, , )

Date and time

All versions of Excel.

Try it

Edit the formula in C2 or change the inputs. The sheet recalculates as you type.

C2
A
B
C
1
Order date
Days
Delivery date
2
03-Mar-2025
10
17-Mar-2025
3

C2 =WORKDAY(A2,B2) returns 17-Mar-2025

How WORKDAY works

WORKDAY returns the date that is a set number of working days away from a start date. Saturdays, Sundays and any holidays you list are skipped. Use it for delivery dates, payment due dates, project milestones and service deadlines. =WORKDAY(A2,10) with Monday 3 March 2025 returns Monday 17 March 2025.

The three arguments

  • start_date is where you start counting. It is not counted itself: WORKDAY(A2,1) is the next working day after A2, not A2.
  • days is the number of working days to move. Use a negative number to go backwards, which is how you find a "start by" date from a deadline: =WORKDAY(B2,-5).
  • holidays is an optional range of dates to skip as well. Keep it in a fixed range, such as $F$2:$F$12, or in a named range.

The result is a serial number. Format the cell as a date to read it.

Starting on a weekend

If the start date is a Saturday or Sunday, WORKDAY begins counting from the next working day. =WORKDAY(DATE(2025,3,15),1) starts on Saturday 15 March and returns Monday 17 March: the first working day after the start date. That is correct, but it surprises people who expect the answer to be Tuesday. If you need the start date counted when it is a working day, move the start back one day first: =WORKDAY(A2-1,1).

Weekends and holidays

WORKDAY always uses a Saturday and Sunday weekend. For a different weekend, use WORKDAY.INTL. Holidays must be real dates in a range. If a holiday falls on a weekend, it makes no difference, and if the result lands on a holiday the function simply continues to the next working day.

Useful patterns

  • Payment due in 30 working days: =WORKDAY(A2,30,Holidays).
  • Next working day: =WORKDAY(A2,1).
  • Previous working day: =WORKDAY(A2,-1).
  • Is a date a working day: =WORKDAY(A2-1,1,Holidays)=A2.
  • Last working day of the month: =WORKDAY(EOMONTH(A2,0)+1,-1,Holidays).

WORKDAY and NETWORKDAYS

WORKDAY gives the date after N working days. NETWORKDAYS counts the working days between two dates. They use the same rules, so each can check the other. NETWORKDAYS counts both ends, so NETWORKDAYS(A2,WORKDAY(A2,10)) returns 11.

Arguments

start_date
The date to count from. The start date itself is not counted as one of the days.
days
The number of working days to move. Positive goes forward, negative goes back, and a fraction is cut off. 10 means ten working days after the start date.
holidaysoptional
A range of dates to treat as non-working days, such as F2:F10. Use real dates. A holiday on a weekend changes nothing.

Examples

Each example is a live sheet. Change the inputs or the formula and watch the result.

Example 1

Ten working days after a start date

C2 =WORKDAY(A2,B2)

Result: 17-Mar-2025

Ten working days after Monday 3 March is Monday 17 March 2025. The weekend of 8 and 9 March is skipped.

C2
A
B
C
1
Order date
Days
Delivery date
2
03-Mar-2025
10
17-Mar-2025
3

C2 =WORKDAY(A2,B2) returns 17-Mar-2025

Example 2

Skip a public holiday

C2 =WORKDAY(A2,B2,E2)

Result: 18-Mar-2025

The holiday on Monday 10 March is not a working day, so the tenth working day moves one day later, to Tuesday 18 March.

C2
A
B
C
D
E
1
Order date
Days
Delivery date
Holiday
2
03-Mar-2025
10
18-Mar-2025
10-Mar-2025
3

C2 =WORKDAY(A2,B2,E2) returns 18-Mar-2025

Example 3

Go backwards from a deadline

C2 =WORKDAY(A2,-B2)

Result: 07-Mar-2025

A negative number of days counts back. Five working days before Friday 14 March is Friday 7 March 2025.

C2
A
B
C
1
Deadline
Days needed
Start by
2
14-Mar-2025
5
07-Mar-2025
3

C2 =WORKDAY(A2,-B2) returns 07-Mar-2025

Example 4

Start date on a weekend

B2 =WORKDAY(A2,1)

Result: 17-Mar-2025

Counting from a Saturday, the first working day is Monday 17 March, so one working day after the start is that Monday.

B2
A
B
C
1
Requested (Sat)
Next working day
2
15-Mar-2025
17-Mar-2025
3

B2 =WORKDAY(A2,1) returns 17-Mar-2025

Your turn.

Solve it in the sheet. Every answer is checked, with hints if you need them.

Task 1 of 2

In C2, return the ship-by date: the order date plus the lead time in working days. Fill it down to C4.

Answer in C2, then it fills down to C4.

C2
A
B
C
D
E
F
1
Order date
Lead time (working days)
Ship by
Ship by (with holidays)
Holidays
2
03-Mar-2025
5
10-Mar-2025
3
12-Mar-2025
10
31-Mar-2025
4
28-Mar-2025
3
5

Common mistakes

  • The start date isn't counted. WORKDAY(A2,1) is the day after A2, so a start on a Monday with 5 days returns the following Monday.
  • The result is a serial number. If a cell shows 45733, apply a date format.
  • The holiday range must hold real dates. Text dates are ignored without a warning, and the result comes out too early.
  • Fill-down breaks a holiday range written without dollar signs: E2:E10 becomes E3:E11. Write $E$2:$E$10.
  • The weekend is always Saturday and Sunday. For anything else, use WORKDAY.INTL.

Questions people ask

How do I add business days to a date in Excel?

Use `=WORKDAY(A2,10)` to move ten working days forward. Add a holiday range as a third argument to skip public holidays.

How do I subtract working days?

Use a negative number: `=WORKDAY(A2,-5)` is five working days before A2.

Does WORKDAY count the start date?

No. It counts from the next working day. Use `WORKDAY(A2-1,1)` if you want a working-day start date to count as day one.

How do I find the last working day of a month?

Use `=WORKDAY(EOMONTH(A2,0)+1,-1)`. It starts on the first of the next month and steps back one working day. Add a holidays range if needed.

What is the difference between WORKDAY and WORKDAY.INTL?

WORKDAY always treats Saturday and Sunday as the weekend. WORKDAY.INTL lets you choose the weekend days.

Learn WORKDAY in a real sheet.

WORKDAY is taught in Dates and financial modelling, lesson 7: Working days and deadlines. Each lesson is a short, graded exercise like the one above.