Example 1
Ten working days after a start date
C2 =WORKDAY(A2,B2)
Result: 17-Mar-2025
Ten working days after Monday 3 March is Monday 17 March 2025. The weekend of 8 and 9 March is skipped.
C2 =WORKDAY(A2,B2) returns 17-Mar-2025
Returns the date a given number of working days before or after a start date, skipping weekends and any holidays you list.
Syntax
=WORKDAY(, , )
All versions of Excel.
Try it
Edit the formula in C2 or change the inputs. The sheet recalculates as you type.
C2 =WORKDAY(A2,B2) returns 17-Mar-2025
WORKDAY returns the date that is a set number of working days away from a start date. Saturdays, Sundays and any holidays you list are skipped. Use it for delivery dates, payment due dates, project milestones and service deadlines. =WORKDAY(A2,10) with Monday 3 March 2025 returns Monday 17 March 2025.
WORKDAY(A2,1) is the next working day after A2, not A2.=WORKDAY(B2,-5).$F$2:$F$12, or in a named range.The result is a serial number. Format the cell as a date to read it.
If the start date is a Saturday or Sunday, WORKDAY begins counting from the next working day. =WORKDAY(DATE(2025,3,15),1) starts on Saturday 15 March and returns Monday 17 March: the first working day after the start date. That is correct, but it surprises people who expect the answer to be Tuesday. If you need the start date counted when it is a working day, move the start back one day first: =WORKDAY(A2-1,1).
WORKDAY always uses a Saturday and Sunday weekend. For a different weekend, use WORKDAY.INTL. Holidays must be real dates in a range. If a holiday falls on a weekend, it makes no difference, and if the result lands on a holiday the function simply continues to the next working day.
=WORKDAY(A2,30,Holidays).=WORKDAY(A2,1).=WORKDAY(A2,-1).=WORKDAY(A2-1,1,Holidays)=A2.=WORKDAY(EOMONTH(A2,0)+1,-1,Holidays).WORKDAY gives the date after N working days. NETWORKDAYS counts the working days between two dates. They use the same rules, so each can check the other. NETWORKDAYS counts both ends, so NETWORKDAYS(A2,WORKDAY(A2,10)) returns 11.
10 means ten working days after the start date.F2:F10. Use real dates. A holiday on a weekend changes nothing.Each example is a live sheet. Change the inputs or the formula and watch the result.
Example 1
C2 =WORKDAY(A2,B2)
Result: 17-Mar-2025
Ten working days after Monday 3 March is Monday 17 March 2025. The weekend of 8 and 9 March is skipped.
C2 =WORKDAY(A2,B2) returns 17-Mar-2025
Example 2
C2 =WORKDAY(A2,B2,E2)
Result: 18-Mar-2025
The holiday on Monday 10 March is not a working day, so the tenth working day moves one day later, to Tuesday 18 March.
C2 =WORKDAY(A2,B2,E2) returns 18-Mar-2025
Example 3
C2 =WORKDAY(A2,-B2)
Result: 07-Mar-2025
A negative number of days counts back. Five working days before Friday 14 March is Friday 7 March 2025.
C2 =WORKDAY(A2,-B2) returns 07-Mar-2025
Example 4
B2 =WORKDAY(A2,1)
Result: 17-Mar-2025
Counting from a Saturday, the first working day is Monday 17 March, so one working day after the start is that Monday.
B2 =WORKDAY(A2,1) returns 17-Mar-2025
Solve it in the sheet. Every answer is checked, with hints if you need them.
Task 1 of 2
In C2, return the ship-by date: the order date plus the lead time in working days. Fill it down to C4.
Answer in C2, then it fills down to C4.
WORKDAY(A2,1) is the day after A2, so a start on a Monday with 5 days returns the following Monday.45733, apply a date format.E2:E10 becomes E3:E11. Write $E$2:$E$10.Use `=WORKDAY(A2,10)` to move ten working days forward. Add a holiday range as a third argument to skip public holidays.
Use a negative number: `=WORKDAY(A2,-5)` is five working days before A2.
No. It counts from the next working day. Use `WORKDAY(A2-1,1)` if you want a working-day start date to count as day one.
Use `=WORKDAY(EOMONTH(A2,0)+1,-1)`. It starts on the first of the next month and steps back one working day. Add a holidays range if needed.
WORKDAY always treats Saturday and Sunday as the weekend. WORKDAY.INTL lets you choose the weekend days.
WORKDAY is taught in Dates and financial modelling, lesson 7: Working days and deadlines. Each lesson is a short, graded exercise like the one above.