Returns the number of days between two dates on a 360-day year of twelve 30-day months, as used in some accounting and interest calculations.

Syntax

=DAYS360(, , )

Date and time

All versions of Excel.

Try it

Edit the formula in C2 or change the inputs. The sheet recalculates as you type.

C2
A
B
C
1
Start
End
Days (30/360)
2
31-Jan-2025
31-Mar-2025
60
3

C2 =DAYS360(A2,B2) returns 60

How DAYS360 works

DAYS360 counts the days between two dates as if every month had 30 days and every year had 360. =DAYS360(DATE(2025,1,15),DATE(2026,1,15)) returns 360, and a six-month gap is always 180. Some bond markets, loan agreements and accruals use this convention because it makes interest arithmetic tidy: a month is always one twelfth of a year.

The three arguments

  • start_date and end_date are real dates. Dates built with DATE are safest. If the end date is earlier than the start date, the result is negative.
  • method chooses how the 31st and the end of February are treated. Leave it out, or use FALSE, for the US method. Use TRUE for the European method.

US method (default)

If the start date is the 31st, it becomes the 30th. If the start date is the last day of February, it becomes the 30th as well. If the end date is the 31st and the start date is then the 30th, the end date becomes the 30th. Otherwise the end date stays the 31st.

European method

Any start or end date that falls on the 31st becomes the 30th. There is no special rule for February. The two methods agree most of the time and differ mainly around month-ends. DAYS360(DATE(2025,2,28),DATE(2025,3,31)) returns 30 with the US method and 32 with the European method.

Using it for interest

A typical simple-interest accrual is principal x rate x days / 360: =B2*C2*DAYS360(D2,E2)/360. That makes each full month worth exactly one twelfth of the annual interest. Check your agreement or policy for the convention it names. A "30/360" basis is what DAYS360 reproduces, and "actual/365" is not.

DAYS360, DAYS and YEARFRAC

DAYS and plain subtraction return actual calendar days. DAYS360 returns the 30-day-month count. For the fraction of a year on common conventions, YEARFRAC has a basis argument that includes 30/360, so =YEARFRAC(A2,B2,0) matches =DAYS360(A2,B2)/360 for the US method.

Remember

Don't use DAYS360 for ages, service lengths or deadlines. Those need real days, and DATEDIF or subtraction is the right tool.

Arguments

start_date
The first date. Use a cell holding a date or a date built with DATE.
end_date
The second date. If it is earlier than the start date, the result is negative.
methodoptional
Which rule to use for month-end dates. FALSE or omitted is the US (NASD) method. TRUE is the European method, which turns any 31st into the 30th.

Examples

Each example is a live sheet. Change the inputs or the formula and watch the result.

Example 1

Two month-ends on the US method

C2 =DAYS360(A2,B2)

Result: 60

Two months of 30 days each. A real calendar count would be 59.

C2
A
B
C
1
Start
End
Days (30/360)
2
31-Jan-2025
31-Mar-2025
60
3

C2 =DAYS360(A2,B2) returns 60

Example 2

A full year

C2 =DAYS360(A2,B2)

Result: 360

Every year is 360 days on this basis.

C2
A
B
C
1
Start
End
Days (30/360)
2
15-Jan-2025
15-Jan-2026
360
3

C2 =DAYS360(A2,B2) returns 360

Example 3

The European method around February

C2 =DAYS360(A2,B2,TRUE)

Result: 32

The European method keeps 28 February as day 28 and turns 31 March into the 30th, so the count is 32. The US method would return 30.

C2
A
B
C
1
Start
End
Days (European)
2
28-Feb-2025
31-Mar-2025
32
3

C2 =DAYS360(A2,B2,TRUE) returns 32

Your turn.

Solve it in the sheet. Every answer is checked, with hints if you need them.

Task 1 of 2

In E2, return the number of days from C2 to D2 on a 30/360 basis.

Answer in E2.

E2
A
B
C
D
E
F
1
Principal
Rate
Start
End
Days (30/360)
Interest
2
12000
6.0%
15-Jan-2025
15-Jul-2025
3
4
5

Common mistakes

  • DAYS360 is not an actual day count. Don't use it for ages, deadlines or pay periods.
  • The default method is the US one. If your contract says European 30E/360, set the third argument to TRUE.
  • The result is negative when the end date is before the start date. Swap the dates if you want a positive number.
  • Text dates can fail or be read the wrong way round on another locale. Build dates with DATE.

Questions people ask

What does DAYS360 do in Excel?

It counts the days between two dates on a calendar where every month has 30 days, so a year has 360 days.

Why would I use DAYS360 instead of subtracting dates?

Some interest and accrual conventions, often called 30/360, require it. Plain subtraction gives actual days.

What is the difference between the US and European methods?

They treat the 31st and the end of February differently. Use `TRUE` for the European method, and leave the argument out for the US method.

How do I calculate interest on a 30/360 basis?

Multiply principal by rate by `DAYS360(start,end)`, then divide by 360.

Learn DAYS360 in a real sheet.

Tracks take you from the basics to modelling, one graded exercise at a time.